Ask what a wind farm owns and the answer sounds physical: turbines, a lease, a connection. Ask a lender and the answer is different. The lender owns a claim on a set of contracts that, together, are supposed to produce cash for fifteen years.
A project company is often a shell with a licence, a site and a stack of agreements. It has little history and few tangible assets. What it has is a documented promise of revenue, detailed enough that a third party can lend against it. The contracts are not paperwork around the infrastructure. They are what makes the infrastructure bankable.
The stack
A project finance structure is a set of agreements that allocate specific risks to specific parties. The list below is typical, not universal. The important thing is not the names but the gaps between them: every contract covers something, and the project carries whatever is left.
01
Offtake or power purchase agreement
A buyer commits to a volume at a price for a term. In CGF's carbon offtakes, CGF buys credits at a fixed volume, price and term.
Limit / Moves volume and price risk to the buyer — if the buyer can pay, and if the volume is actually delivered.
02
Contract for difference
The parties exchange the difference between a reference price and a strike price for an eligible volume.
Limit / Moves price or policy risk. Leaves basis risk, volume risk and the need to verify the volume.
03
Engineering, procurement and construction
Fixes a price, a schedule and a performance specification for the build.
Limit / Only as strong as the contractor's balance sheet and the guarantees behind it.
04
Operations and maintenance
Sets availability, efficiency and reporting obligations for the operating asset.
Limit / Does not restore a market, a permit or a community's trust.
05
Supply agreement
Locks in fuel, feedstock or component supply, often with a price mechanism.
Limit / Introduces a new counterparty and a new index into the risk stack.
06
Interconnection agreement
Defines rights and cost responsibility at the boundary between project and grid.
Limit / Does not guarantee that the grid will accept power when the project wants to send it.
07
Credit support
Guarantees, letters of credit and collateral make a contractual promise credible.
Limit / Adds liquidity demands that can arrive exactly when the project can least afford them.
How certainty becomes debt capacity
A lender does not lend against a forecast. It lends against the part of the forecast it can enforce. That is why a contract with a creditworthy buyer can support more debt than the same project selling into a merchant market — even if the expected revenue is identical.
Illustrative arithmetic
A simplified revenue case, not a project. No CGF transaction is described, and no result here is a forecast.
- Eligible volume
- 250,000 tCO₂e / year
- Strike price
- $100.00 / tCO₂e
- Contracted revenue
- $25,000,000
- Operating costs assumed
- 30%
Cash available for debt service is about $17,500,000. At a 1.5× coverage ratio, that supports roughly $11,666,667 of annual debt service. Amortized at 6% over 15 years, it supports about $113 million of debt.
Lower the strike to $80.00 and the same project supports about $91 million. A difference of $20.00 per tonne moves debt capacity by nearly $23 million before construction costs move at all.
Assumptions: 30% operating costs, 1.5× debt service coverage, 6% interest, 15-year amortization, no taxes, reserves, inflation, fees or working capital. Illustrative only.
Anatomy of a two-way contract for difference
A contract for difference is a hedge, not a purchase. The commodity is sold in the market as usual; the contract settles the distance between the market price and the agreed strike. The Canada Growth Fund's plan describes two versions: one referencing a market price, one referencing a policy price. Both absorb a risk the project cannot price on its own.1
The plan also states that its contracts for difference are structured as two-way contracts. That single word changes the economics: the public counterparty participates in the upside when the reference price rises above the strike, rather than only insuring a floor.1
- Strike price
- The fixed reference level written into the contract. It is not a forecast of the market; it is the price at which the parties agreed to settle.
- Reference price
- The published or observed price the contract measures itself against. The definition, the source and the fallback matter as much as the number.
- Eligible volume
- The quantity that may be settled — output, emissions or credits — and the rules that decide whether it counts.
- Term
- How long the promise lasts. The asset will probably outlive it, which leaves a residual exposure at the end.
- Settlement
- How often, in what currency and on what date the difference is paid. Timing is a credit risk, not an administrative detail.
- Direction
- One-way contracts insure a floor. Two-way contracts also share the upside, so the holder pays when the reference price is above the strike.
The equation
payment = (strike − reference) × eligible volume
At a strike of $100.00 and a reference of $70.00 on 250,000 tonnes, the payment is $7,500,000, from the provider to the holder. If the reference were $130.00, the same contract would run the other way.
Reference price: $70.00
Provider → holder · $7,500,000
Chart of the two-way payment. At the current reference price of $70.00, the payment is $7,500,000, from the provider to the holder.
What a contract cannot fix
Basis risk is the first residual. If the contract references a national carbon index but the project sells regionally, the hedge can perform perfectly while the project loses money. Volume is the second: no output, no eligible volume, no payment. Construction is the third: a well-drafted contract does not pour concrete.
There is also the durability problem. A contract can promise a price for fifteen years; it cannot promise that the policy creating the market survives for fifteen years. It can allocate the consequence of a change in law, but only if someone is willing to accept that consequence today.
And every contract creates a new counterparty. If the provider cannot pay, the holder owns a claim, not a hedge. This is why credit support is not a technical appendix. It is part of the asset.
Seven clauses to read
Not a legal checklist, and not a substitute for advice. But if you want to understand what a contract actually transfers, these are the places to look.
- 01
The reference price and its fallback
Which index, published by whom, on which date, and what happens if it is discontinued or disputed.
- 02
Eligible volume and verification
What counts, who measures it, what evidence is required, and who pays for the measurement.
- 03
Settlement mechanics
The calculation, the invoice, the payment date, the currency and the consequences of a late payment.
- 04
Direction and symmetry
Whether the contract is one-way or two-way, and how the upside is shared when the reference price rises.
- 05
Term, termination and change of law
What ends the contract early, who compensates whom, and what happens if the policy behind the market changes.
- 06
Credit support
Guarantees, collateral, rating triggers and the circumstances in which additional security must be posted.
- 07
Disputes and governing law
Where a disagreement is heard, under which law, and whether expert determination comes before litigation.
A project is not made bankable by adding more contracts. It is made bankable by making the gaps between them visible, pricing the residual honestly, and putting each risk where it can actually be managed.
The tool that follows turns the equation into something you can hold: three inputs, one payment, and a direction that reverses when the reference price crosses the strike.
Sources
Method & source register- 01Corporate Plan Summary 2026-2030
Canada Growth Fund · Information current as of 23 October 2025 · Accessed 13 November 2026
- 02Our Investment Strategy
Canada Growth Fund Investment Management · Undated web page · Accessed 13 November 2026
Cited documents are linked, not reproduced. Figures are reported as published and are not live data.