SignalPath Index / Special project 001
Energy infrastructure · Canada · 23 October 2025
Before thepower flows.
A project does not begin with steel. It begins with promises about price, volume, risk and time that must hold long before a single electron moves.
Two explainers · One price tool · About 20 min
Scroll to energize the lineContinue to the premise
Schematic. Not a real project, site or contract. Public sources, cited.
01/The premise
A project is a promise before it is a line.
7 min read · Editorial
A power line is a physical fact. Before it exists, it is a set of promises: that a site can be permitted, that steel will arrive on schedule, that a buyer will pay an agreed price, that a lender will be repaid, that a community will tolerate the work. Each promise is made by someone, priced by someone, and broken at someone's cost.
Energy infrastructure is capital-heavy and slow. The expensive decisions happen years before revenue, and the risks do not arrive one at a time. They arrive as a permit delay while the interest clock runs, a transformer that ships late, a price that moves against the case, a policy that changes after the contract is signed.
This project follows the sequence — proposal, screening, structuring, construction, operation — and asks the same two questions at every stage: what has to be true, and who carries the cost if it is not?
Why the Canada Growth Fund
The frame comes from two public documents from the Canada Growth Fund: its investment strategy, and its Corporate Plan Summary 2026–2030, whose information is current as of 23 October 2025.1 The fund is described as a $15 billion independent investment fund operating at arm's length from the Government of Canada, managed by CGF Investment Management, a wholly owned subsidiary of PSP Investments. It invests through equity, debt, hybrid instruments, offtake contracts and contracts for difference. It states that it does not provide grants or subsidies, and that it expects to recover its capital on a portfolio basis.
The contracts are the interesting part. A contract for difference does not buy or sell the commodity. It exchanges the difference between a reference price and a fixed strike price for an eligible volume. When the reference is below the strike, the provider pays the holder; when it is above, a two-way contract reverses the payment. One equation moves a large amount of risk — and creates a new set of questions.
This is an explainer, not a prospectus. No project, partner, return or incident is invented here. Where the public record stops, the text says so.
- 15
- $ bn
- 16
- deals
- 7
- $ bn
Fund described in the plan
Independent, arm's length
Transactions announced
As of October 2025
Contract tail-risk limit
Aggregate net exposure
As reported in the Corporate Plan Summary 2026–2030. Not live data.
02/The stage
Five stages. One balance sheet at the end.
A project is not approved once. It is approved repeatedly, by different people, with different information and different exposure. Select a stage to see what has to be true, who carries the risk, and what is still unresolved.
Editorial sequence, not a specific transaction. Stages overlap in practice.
Stage 01 / 05
Months to years
An intention becomes a file.
A project starts as a claim about the future: a technology, a site, a volume, a price. Nothing is built. The first task is to turn the claim into something another party can underwrite.
What changes
Uncertainty is at its widest, and information is cheapest to gather.
What must be true
- The technology has been proven in pilots but is not yet widely adopted - the category the fund describes as Projects.
- Activity happens in Canada, strengthens a Canadian value chain, or keeps Canadian intellectual property in the country.
- There is a plausible path to private capital that would not arrive on the same terms without a public participant.
Where the money is
Development capital, spent before any revenue exists and usually lost if the project stops.
Who carries what
- Project
- Site control, permits, engineering, early development costs.
- Capital
- Usually absent at this stage; the risk is too early to price.
- Public
- May read the file, but has committed no capital and contracted no revenue.
Questions still open
- What exactly is being promised: price, volume, schedule, or all three?
- Which risk has no private buyer at any reasonable price?
- Would the project exist without public participation? If so, why is it here?
Basis: CGF Investment Strategy · CGF Corporate Plan Summary 2026-2030
Stage 02 / 05
Weeks to months
Fit is tested before money moves.
The manager tests the file against published criteria: consistency with the mandate, long-term benefits for Canada, additionality, financial soundness, and sustainability disclosure. The point is a rigorous, fair and repeatable first filter.
What changes
The question changes from 'is this a good project?' to 'is this the right project for this balance sheet?'
What must be true
- The investment advances the fund's mandate and strategic objectives.
- Benefits are likely to reach Canadian workers and the wider economy, not only the sponsor.
- Additionality is credible: private capital would likely not have been secured on the same terms.
- The investment fits a portfolio that targets preservation of capital.
Where the money is
No capital committed. Time, diligence and reputational risk are spent instead.
Who carries what
- Manager
- Screening judgement and the quality of evidence behind it.
- Project
- Cost and delay of diligence, and disclosure of commercial detail.
- Public
- Reputational risk if selection looks arbitrary or additionality is asserted rather than tested.
Questions still open
- Is the Canadian benefit specific or aspirational?
- What evidence supports additionality, and who checked it?
- Which criterion is weakest, and who decided the weakness was acceptable?
Basis: CGF Investment Strategy · CGF Corporate Plan Summary 2026-2030
Stage 03 / 05
Months
The promise gets a price.
Here the project acquires the instruments that make it financeable: equity, debt, hybrids, offtake contracts or contracts for difference. Structuring is the work: each instrument moves a named risk onto a named balance sheet, for a price and a term.
What changes
A commitment can now be described precisely: to whom, for how much, on what condition, until when.
What must be true
- The risk being transferred is named, priced and limited in time.
- Reference price, strike price, eligible volume and settlement rules are written into the contract.
- The structure is acceptable to private co-investors and lenders, or the public share is sized to compensate.
- Tail exposure fits the fund's published limit: aggregate net exposure through contracts in a tail-risk scenario of no more than $7 billion.
Where the money is
The commitment is defined; deployment remains contingent on conditions and construction.
Who carries what
- Project
- Performance, completion, operating cost, and basis risk that no contract removes.
- Capital
- Construction, credit, interest-rate and currency risk, mitigated by terms and covenants.
- Public
- The price or demand risk it has agreed to absorb, plus counterparty and policy risk it cannot contract away.
Questions still open
- Which reference index, and does the project actually sell into it?
- Is the contract one-way or two-way? Who keeps the upside?
- What counts as eligible volume, and who verifies it?
- What happens if the counterparty fails before the term ends?
Basis: CGF Corporate Plan Summary 2026-2030 · CGF Investment Strategy
Stage 04 / 05
One to five years
Commitments become deployments.
A commitment is a promise to fund; a deployment is money that has actually left. Large projects are funded over years, against milestones. This is where schedules slip, costs move, and contracts meet events rather than drafting notes.
What changes
Risk stops being an abstraction: it arrives as a change order, a delay, an invoice.
What must be true
- Cash is released against defined milestones and conditions precedent.
- Completion risk sits with a contractor, an insurer, or the sponsor's contingent equity - not with optimism.
- Interest-rate and currency exposure is hedged or accepted deliberately.
- Termination, step-in and security rights are operational, not theoretical.
Where the money is
Capital is drawn progressively; in any year, deployments may lag commitments and rise over time.
Who carries what
- Project
- Overrun equity, delay costs, and the gap between promised and delivered performance.
- Capital
- Drawdown discipline, security, covenant compliance.
- Public
- Funding availability and the credibility of its own commitment over the term.
Questions still open
- Who pays if the project is late?
- Who funds an overrun, and how much before the structure breaks?
- Which milestones actually release capital?
- What happens if the contractor walks away?
Basis: CGF Corporate Plan Summary 2026-2030
Stage 05 / 05
A decade or more
The line is live. The contract keeps working.
Operation is the longest stage and the least dramatic. The asset produces; the meter measures; the contract settles. The public question shifts from whether the project will be built to whether it is delivering what was promised, at what cost to the balance sheet.
What changes
Payments now flow in both directions, depending on the reference price.
What must be true
- Eligible volume is measured and verified before settlement.
- The reference price is observable and agreed, not negotiated at each settlement.
- Performance against the impact case is tracked, not assumed.
- Exit is possible in principle; as of the plan, the fund had not yet exited any investment.
Where the money is
Operating cash flow, contract settlements, and monitoring against the original impact case.
Who carries what
- Project
- Availability, efficiency, emissions performance and safety.
- Capital
- Settlement, collateral, credit and the durability of the contracted revenue.
- Public
- Tail exposure, policy change, and the reputational cost of a contract that ages badly.
Questions still open
- What does the public get if prices move favourably?
- What happens when the contract term ends?
- Who verifies the impact numbers?
- What would make this contract a mistake, and who would say so publicly?
Basis: CGF Corporate Plan Summary 2026-2030
Source basis: Canada Growth Fund, Corporate Plan Summary 2026–2030, and Our Investment Strategy.
"Commitment" and "deployment" are used in the sense set out in the plan's financial overview: a commitment is an agreement to invest; a deployment is the funding of a prior or concurrent commitment. The distinction matters because a headline number is not money that has left.
03/Close inspection
Read the drawing.
A project is usually presented as one line. In practice it is six responsibilities, each with its own failure mode and its own contract. Select a part. Notice that the settlement layer is not electricity.
Fig. 03 / One line, six responsibilities
Not to scale
The dashes are money, not electricity. The bus is a drawing convention, not a site plan.
Part 01 / 06
Generator
- What it does
- Turns fuel, heat or kinetic energy into electricity. The whole case rests on how much it produces, how reliably, and at what emissions intensity.
- What can go wrong
- Underperformance, outages, and emissions above the design case - the distance between a promised asset and a delivered one.
- What the contract asks
- Performance guarantees, commissioning tests, availability commitments, and the measurement standard that decides whether they were met.
Editorial description. No claim about a specific project, site or contract.
04/The reading room
Two ways to read the machine.
The opening shows the sequence. The two explainers slow it down: first who carries the risk, then how the contract turns a promise into something a lender can underwrite.
The equation
payment = (strike − reference) × volume
Below the strike, the provider pays. Above it, a two-way contract reverses.
Open the tool- 01Who carries the risk?Explainer 01 · Risk allocation · 8 minA risk ledger, the price of accepting risk, what a public balance sheet can absorb, and five questions to ask of any risk transfer.
- 02The contract is the infrastructureExplainer 02 · Project finance · 9 minWhy a project borrows against a contract stack, how certainty becomes debt capacity, and the anatomy of a two-way contract for difference.
- 03A price, twiceInstrument · Interactive · 3 minThree inputs, one equation, and a payment that reverses direction when the reference price crosses the strike. Clearly illustrative.
If you read nothing else
Read the risk ledger. Nine rows, one idea: whatever the contract does not move, someone still holds.
05/Sources & dates
The record, and where it stops.
This edition is built from two public documents, read closely and cited by section. Figures are reported as they appear in those documents; nothing is updated, modelled or described as live.
The project stages and the two explainers are editorial synthesis. Where they describe typical project-finance practice, they say so. Where the public record is silent, they say that too.
Independence
SignalPath Index is an explanatory editorial project built from public documents. It is not an official publication of the Canada Growth Fund, Canada Growth Fund Investment Management, PSP Investments or the Government of Canada, and nothing here is investment, legal, tax or accounting advice.
- 01Corporate Plan Summary 2026-2030Canada Growth FundInformation current as of 23 October 2025Accessed 13 November 2026Primary source for mandate, investment instruments, contract mechanics, risk framework, funding and commitments.
- 02Our Investment StrategyCanada Growth Fund Investment ManagementUndated web pageAccessed 13 November 2026Primary source for investment criteria, focus areas, financial structures and the investment process.
As of
23 October 2025
Information date of the cited plan
Updated
13 November 2026
Sources accessed 13 November 2026
Documents are linked, not reproduced. © 2026 SignalPath Index. Original text and diagrams.
End/End of the opening
The rest is the reading.
Two explainers and one instrument. Everything is sourced, dated and labelled. Nothing here is a live project or an offer.